The BCO calls Cat A fit-out a major source of waste. How to plan trimless, plastered-in lighting so it is fitted once and not stripped out.

Trimless lighting and Cat A waste

On 9 November 2026 the British Council for Offices published How to Deliver Viable Office Buildings in 2027, written by Gardiner & Theobald and Turner & Townsend alinea. It found the average cost of building a Central London office rose from £380 per sq ft in 2020 to £540 per sq ft in 2025, an increase of 42%. The BCO says the report "highlights Cat A fit-out as one of the industry's biggest sources of waste, with newly installed finishes and services routinely stripped out by occupiers shortly after completion" (BCO).

Trimless lighting is plastered into the ceiling. Once it is in, it is part of the finish. That makes it one of the details most worth getting right first time, and one of the most wasteful to install and then rip out. This guide looks at how to plan trimless lighting so it is fitted once.

Why plastered-in details are vulnerable

Trimless fittings are set into plasterboard and skimmed over, so the edge disappears. Removing or moving them means cutting out board, making good, re-skimming and redecorating. If a Cat A ceiling is taken out for a tenant's Cat B design, any trimless detail in it goes too. For how trimless lighting is installed, see how trimless lighting is installed and the installation sequence.

Where trimless earns its place

The BCO report says "every element should earn its place". In offices, trimless details tend to make most sense where they are least likely to change:

AreaLikelihood of changeTrimless approach
Reception and lobbyLow, landlord controlledStrong case for trimless. See trimless receptions
Lift lobbies and coresLowTrimless downlights and lines work well
CorridorsLow to mediumSee trimless corridors
Toilets and showersLowCheck IP ratings for wet zones
Open-plan office floorsHigh, often refittedConsider whether trimless should wait for the tenant
Meeting roomsDepends on tenantAgree with the occupier before plastering in

Owner-delivered fit-out

One of the report's recommendations is to "consider owner-delivered fit-out where demand is clear, to cut waste and shorten occupation programmes". Where the landlord fits out to a known occupier brief, trimless details can be designed once, with the final layout. Where the occupier is unknown, it may be better to keep trimless to landlord areas and leave the office floors for later.

Plan for change

Even where trimless is used, it can be detailed to cope with change:

  • Replaceable modules. Choose fittings where the LED module and driver can be changed from below, without cutting the plaster. See trimless lighting maintenance
  • Controls. Addressable controls let scenes and groups be changed in software rather than rewiring. See trimless lighting controls
  • Grid logic. A layout based on the ceiling and furniture grid is easier to reuse
  • Records. Keep accurate drawings and BIM data of every fitting. See BIM details for trimless lighting

Get the detail right first time

Making good a failed trimless detail is also waste. Cracks, poor joints and visible edges often lead to rework. To reduce the risk:

Alternatives where change is likely

Where a ceiling may be replaced, consider details that are easier to move or reuse:

Refurbishment

Many office projects reuse existing buildings, and the BCO report recommends deciding early which parts of existing buildings are worth retaining on reuse schemes. Trimless details can be added in refurbishments where new ceilings are being built. See trimless lighting in refurbishment and trimless lighting in listed buildings.

Cost

Trimless details add work for the plasterer and need careful coordination. They are worth it where they last. See trimless lighting cost.

Checklist

  • Ask who controls each area, and how likely it is to change
  • Use trimless in landlord areas and spaces with a known brief
  • Choose fittings with replaceable modules and drivers
  • Use addressable controls for flexibility
  • Mock up and approve the detail before full installation
  • Keep accurate records for future occupiers

Questions to ask at Cat A stage

  • Is there a known occupier, and has their brief been shared?
  • Which areas will the landlord keep control of after letting?
  • Will the ceiling stay, or is it likely to be replaced at Cat B?
  • Can fittings be maintained from below without damage to the plaster?
  • What records will be handed over to the occupier's design team?
  • Has the occupier's furniture layout been agreed, so fittings line up with desks and rooms?

How 299 Lighting can help

299 Lighting supplies trimless and recessed lighting for offices, with bespoke solutions and project support from design to installation. See our recessed lighting and linear lighting, or send us your drawings.

Planning a trimless ceiling?

Send us your reflected ceiling plan. We'll come back with a shortlist, plaster-in details and lighting calculations.

Start a project →

Frequently asked questions

What did the BCO say about Cat A fit-out?

Its 9 November 2026 report highlights Cat A fit-out as one of the biggest sources of waste, with new finishes and services often stripped out soon after completion.

Where does trimless lighting make most sense in offices?

In areas unlikely to change, such as receptions, lift lobbies, cores and corridors.

Can trimless fittings be maintained without cutting the plaster?

Many can, if the LED module and driver are replaceable from below. Check this before specifying.

What is the alternative where a ceiling may change?

Trimmed recessed downlights, suspended fittings or retrofitting existing luminaires can be easier to move or reuse.